Hartex Engineering also offers a number of solutions to upgrade your old pit and turn it into a modern well-equipped prefabricated pit complete with a heavy vehicle jacking system which can cater for the wheel base of your whole fleet without the old fashioned bridgehead that was previously required.
All of Hartex's Pit depths are made to the new RMS standards.
State Transit Authority
First steps are to break the existing concrete on floor level to accommodate the brake and suspension testers
Layout steel work to carry the jacking system and locate jack runs on the workshop pit wall and secure to wall or structure
Lay formwork on pit floor for concreting, pour concrete to form the new finished floor. Weld in top deck steel work and paint pit in two pack epoxy. Pit jacks plumbed to external power
The finished pit is now complete with state of the art Diagnostic Equipment, Jacking System, Lighting, Ventilation & Water Recycling
Old workshop pit before upgrade & restoration
Newly completed workshop pit