Hartex Engineering also offers a number of solutions to upgrade your old pit and turn it into a modern well-equipped prefabricated pit complete with a heavy vehicle jacking system which can cater for the wheel base of your whole fleet without the old fashioned bridgehead that was previously required.
Check out our projects section for details and further information.
All of Hartex’s Pit depths are made to the new RTA standards.
First steps are to break the existing concrete on floor level to accommodate the brake and suspension testers.
Layout steel work to carry the jacking system and locate jack runs on the workshop pit wall and secure to wall or structure.
Lay formwork on pit floor for concreting, pour concrete to form the new finished floor. Weld in top deck steel work and paint pit in two pack epoxy. Pit jacks plumbed to external power
The finished pit is now complete with state of the art Diagnostic Equipment, Jacking Systems, Lighting, Ventilation & Water Recycling.